Council approves pay request and $49,972.80 change order for 2nd Street project
Summary
Wessington Springs City Council approved Pay Request #6 from H & W for $23,626.50 and Change Order #1 for $49,972.80 on the 2nd Street project; Brosz Engineering and Mid Dakota provided project updates to the Council.
Get email alerts on the 2nd Street Project topic
No spam. Unsubscribe anytime.
The Wessington Springs City Council approved two payments related to the 2nd Street reconstruction on Oct. 6, 2025. Council accepted Pay Request #6 from H & W (H&W Contracting LLC) in the amount of $23,626.50 and approved Change Order #1 for $49,972.80 after the contractor signed and returned the change order documents.
Brad Lawrence, representing Brosz Engineering, met with the Council to discuss the 2nd Street Project and provided the engineering update recorded in the minutes. Scott Gross from Mid Dakota also updated the Council on Mid Dakota's portion of the project and the utility hookups. The minutes list the motions and roll-call results: both the pay request and the change order were approved with votes recorded as Ayes: 5, Nays: 0 (motion carried).