Commission approves UPS replacement for county servers using insurance funds (PO 8039)
Summary
IT staff described UPS failures during a generator test and sought approval to replace the unit; commissioners approved purchase order 8039 to buy a replacement UPS using insurance claim proceeds; staff said battery life is roughly three years and the unit will be validated during generator testing.
Get email alerts on the It Infrastructure topic
No spam. Unsubscribe anytime.
Joseph Tongwe of the IT department asked the commission to approve replacement of the main uninterruptible power supply (UPS) in the county's data center after the unit failed to sustain power during a recent generator shutdown. Staff obtained competitive quotes and plan to use insurance proceeds from a claim related to last year's flood to pay for the replacement.
Tongwe explained testing and validation plans for the new unit, including electrician verification and a live generator test once the new UPS is installed. "The battery, I think, is about 3 years," Tongwe said when commissioners asked about longevity. Commissioner moved and seconded approval of PO number 8039 for the purchase; the motion passed by voice vote.
Provenance: item introduced at SEG 660 and the motion recorded at SEG 804–813.