Council approves $65,514 in change orders for All Seasons Arena reconstruction

North Mankato City Council · March 3, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City Administrator McCann reported change orders totaling $65,514.42 for the All Seasons Arena project, with reserves temporarily reduced to $18,171.12 and expected to recover after material sales and scope changes; McCann said the project is about 50% complete.

The council on March 3 adopted Res. No. 30-25 approving change orders for All Seasons Arena Project No. 11075. City Administrator McCann reported the change orders "came from Metcon, Rink Tec, Malterer Mechanical, Laketown Electric, and Dirt Merchant for a total change order of $65,514.42," and that the reserve balance would be $18,171.12 after applying the changes. McCann said the ASA Board recommended the change orders and that subsequent sales and scope adjustments should restore the balance to about $57,507.

Council Member Whitlock asked how close the project was to completion; McCann said "the project is about 50% completed" and that the hope is the next phase will focus on a newer rink with fewer surprises. The motion to approve the change orders passed unanimously.