Board hears audit of auditorium lighting, E-Rate internet work and ESG completions

Hardy County Board of Education · August 4, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Staff reported E-Rate Internet cabling slated for Moorefield Elementary and said ESG work on lighting and building envelope is complete; auditorium dimmer issues require parts and a lift for installation.

District staff told the board that the E-Rate internet project will run Ethernet/fiber to Moorefield Elementary and that lighting and building-envelope work under the district's ESG contractor are substantially complete. Staff said the auditorium lighting requires investigation of dimmers and drivers and that a vendor has ordered 12 LED kits to test whether replacement parts or drivers are needed: "They ordered 12 kits that they are purchasing for us," staff said.

Board members asked whether the auditorium lighting would be finished before the first day of school; staff replied the timeline depends on vendor pricing and electrician availability. The superintendent said the district has coordinated walkway construction and conduit runs so the internet cabling will be installed concurrently when that site work occurs.