Council reviews final plans and an $801,309 revised cost for Estates waterline and North Pump Station loop
Summary
Staff presented final plans to replace the last asbestos-concrete main on Estates Road with 8-inch PVC and to loop the North Pump Station with a 12-inch line; the combined opinion of cost rose from $353,998 to $801,309 after scope additions including service replacements and excavation.
Get email alerts on the Water Infrastructure topic
No spam. Unsubscribe anytime.
Patrick Hubbard presented final designs for two combined CIP projects: replacing a 6-inch asbestos-concrete waterline on Estates Road with 8-inch PVC and adding a 12-inch loop at the North Pump Station to remove a dead-end main and reduce routine flushing. He said combining the projects improves bidding and operational value.
Hubbard told the council the original opinion of cost for the two projects combined was $353,998; the revised opinion of cost is now $801,309, an increase attributable to scope changes such as excavating and abandoning the redundant parallel main, adding a butterfly valve for improved hydraulic control and replacing service lines to the meter for many homes. He also explained the replacement will eliminate a brittle asbestos-concrete main and reduce long-term maintenance and hazmat concerns.
Next steps: finalize design, advertise/bid (estimated ~60 days), and complete construction (estimated ~120 days).