County approves CM/GC contract with Big Valley Construction for EMS Station 1 preconstruction

Grand County Board of County Commissioners · September 17, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Project manager Jeff Hickam presented site-prep and contract details for EMS Station 1, including geotechnical borings not to exceed $9,800 and a $39,500 preconstruction lump-sum; the board approved a contract with Big Valley Construction and adjusted insurance thresholds for preconstruction.

Grand County project manager Jeff Hickam updated commissioners on EMS Station 1 planning and requested approval for a construction-manager/general-contractor (CM/GC) agreement with Big Valley Construction. He said staff selected a geotechnical firm to perform test borings with work "not to exceed $9,800" and cited a preconstruction lump sum of $39,500 for Big Valley to complete the planning-phase work.

Hickam also asked the board to lower the professional-liability threshold for the preconstruction portion from $1.2 million to $1,000,000 because Big Valley is overseeing engineers rather than providing engineering services directly; staff said Big Valley meets other insurance requirements and construction-phase insurance will exceed minimums. Commissioners thanked staff and Big Valley representatives and approved the contract and authorization for the chair to sign.