Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Lagoon Project topic

No spam. Unsubscribe anytime.

Council awards lagoon contract to Arrow Restoration to meet Dec. 31 grant deadline

Plevna Town Council · December 8, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

After an update from Brosz Engineering that contractors can start in December, the Plevna Town Council voted 4–0 to award the lagoon construction contract to Arrow Restoration and agreed to a special meeting Dec. 30 to approve invoices ahead of a Dec. 31, 2025 grant deadline.

Shannon Hewson of Brosz Engineering apologized to the council "for how long the Lagoon project has taken" and said the contractors are still willing to begin work in December. Brosz told the council the firm would absorb extra winter-work costs and cover additional design work costs the firm had already incurred.

To satisfy a grant deadline on Dec. 31, 2025, Brosz advised the town to award the contract to the contractor as bid this past summer and then process a contract change order. Councilman Jason Oberlander moved to award the contract to Arrow Restoration as bid; the motion carried 4–0. The council scheduled a special meeting for Dec. 30, 2025, at 7:00 p.m. to approve any invoices necessary to meet the grant deadline.

Council recorded that Brosz would cover extra cost exposure for winter work and additional design expenses, and that awarding the contract now was a prerequisite to invoicing against grant milestones before year-end.