New clinic in Manila moves forward; sheetrock scheduled for early March
Summary
The new clinic project in Manila is advancing: yard grading is largely complete, sheetrock installation is slated for the first week of March, and county staff member Jesse Platt ran ethernet cables that saved time and money for the project.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
The Municipal Building Authority was updated that work on the new clinic is continuing. Meeting minutes note that yard grading for the project is essentially complete and that contractors plan to begin sheetrock installation in the first week of March.
Meeting records also state that Jesse Platt, with assistance from the county IT department, ran ethernet cabling for the clinic; the minutes say that action saved project time and money. No schedule changes or budget adjustments were presented to the board at this meeting.