Vendor seeks to replace elementary windows and repair masonry to stop leaks
Summary
A design-build contractor recommended full-size energy-efficient windows plus tuckpointing and a new coping cap to stop water infiltration at the elementary school; the district was urged to contract now to secure subcontractor availability and to expect preliminary budget estimates to be refined after site walks.
Get email alerts on the Elementary Windows topic
No spam. Unsubscribe anytime.
Cameron, a presenter from Performance Services, told the Beecher CUSD 200U facilities committee that the elementary school needs full-size energy-efficient windows and masonry repairs to stop water intrusion.
"I'm Cameron from Performance Services," he said, and described the company's 27-year track record and recent addition of an architectural arm. He presented a preliminary budget and emphasized that the estimate is a budget figure because subcontractors had not yet completed a site walk.
Cameron explained the recommended scope: remove plywood infill and residential-style windows, install full-size, energy-efficient windows, perform tuckpointing around the building crown and replace the coping cap to prevent water from seeping into sills. He warned that partial fixes risk repeat failures and follow-up calls years later, saying he did not want the district to "have to call me in 5 years and say, hey... the sill around there is starting to deteriorate, because water is now seeping down." (Cameron)
On procurement, Cameron said hard prices usually come in about 5% under budget pricing after subcontractors walk the site and that Performance Services typically presents open-bid results so the district can consider local firms. He also described a guaranteed-savings contract workflow and told the committee the firm offers a "no change order guarantee" once hard prices are set.
The committee asked about timeline and mobilization; Cameron said a 5% mobilization payment and a payment schedule by percent complete (25/50/75/100) are typical, and that ordering sooner helps secure lower prices and subcontractor availability for summer work.
The committee did not take a vote but directed staff to obtain a roofing inspection and to schedule follow-up meetings before the next board meeting.