Committee weighs cost, change-order risk and schedule; recommends January decision
Summary
Members discussed GRP's budgetary numbers, change-order risk and whether to stage repairs; staff recommended the committee make a January recommendation to the full board rather than a rushed December vote.
Get email alerts on the Procurement topic
No spam. Unsubscribe anytime.
Committee members pressed GRP and staff on pricing, possible change orders, and work schedule. Scott said GRP's figures were budgetary but based on contractor walk-throughs and that contractors could perform the work during the summer; a committee member emphasized concern that opening walls or ceilings could reveal additional damage and trigger costly change orders.
Staff recommended against a rushed December board vote and told the committee, "I would say this is gonna be a January decision by this board." Committee members discussed staging work (A–C now, D/E later) versus doing larger tuckpointing projects across buildings in a later budget cycle. Staff flagged other upcoming capital needs — boilers and a junior-high roof — as constraints on available funds.