GRP recommends window replacements and parapet repairs at elementary school

Beecher CUSD 200U Facilities Committee · December 4, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

GRP representative Scott Ingram told the Beecher CUSD 200U facilities committee that water intrusion at the elementary school appears driven by roof-edge (parapet/coping) failures and proposed replacing second-floor windows and repairing parapet/coping to stop leaks.

The Beecher CUSD 200U facilities committee heard a presentation from GRP representative Scott Ingram proposing replacement of second-floor elementary windows alongside masonry and roof-edge repairs to stop ongoing water intrusion. Staff introduced the proposal and provided committee members with GRP's line-item pricing and photos for several exterior walls; Scott said the district's prior spray-foam roofing and degraded parapet/coping likely created the leak path.

Scott Ingram summarized the diagnosis: "Ultimately, you have a problem with water coming into the building." He explained that while the existing windows are in poor visual condition, GRP's view is the water is entering because of parapet/roof-edge issues and recommended tying the roof into a new seam and adding a metal cap to prevent future intrusion. He also recommended matching the windows to the first-floor units and discussed options for glass versus insulated panels, noting similar R-values and pricing: "Our goal is to match the windows that you already have on the 1st Floor."