Board OKs amendment to force-main design for North Tully Road pump station

Lockeford Community Services District Board of Directors · May 14, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Directors approved an amended scope to design a force main that will be bored under the creek rather than attached to the bridge; the motion passed unanimously.

The board approved an amendment to the design scope for the North Tully Road Pump Station force main so the plan will now include boring under the creek instead of attaching the pipe to the bridge.

KSN's Steve Pechin explained the change in approach; Nina Chandler moved to approve the amendment and Fred Fickert seconded. The motion carried unanimously, authorizing KSN and staff to complete the detailed design for the revised alignment.

The board did not discuss a revised cost estimate in the meeting record. Staff will proceed with design work reflecting the boring-under-creek approach.