Commission approves $33,000 in change orders after unexpected clay tile discovered during 1st Street work
Summary
Contractor crews found clay tile sewer pipe under 1st Street at 6th Avenue NW; the commission approved change orders adding roughly $33,000 to the project to upsize manhole connections and avoid delay.
Get email alerts on the Street Work topic
No spam. Unsubscribe anytime.
City engineering staff described an unanticipated underground condition on the 1st Street Reconstruction (Street Improvement District 236): crews encountered a 24-inch clay tile pipe and a tight box structure tied to a manhole at 6th Avenue NW, not the PVC the plans anticipated.
Riley summarized photos and excavation work, concluding that removing and upsizing the connection was the least-delay option. "Net increase for this to the project was roughly $33,000," Riley said. Commissioner Sjoberg moved to approve change orders 1 and 2 to address the condition and the motion carried on roll call.
Staff explained the work required jackhammering, extra man-hours in the manhole and limited additional schedule impact; the federal DOT schedule did not grant a lengthy time extension. The change-order approval authorizes the contractor to complete the corrective work and proceed toward project close-out steps.