Commission approves Car Coatings contract for South Side Reservoir, adds $37,450 to plant budget
Summary
The commission awarded a $163,450 contract to Car Coatings LLC for the South Side Reservoir coating project and approved a $37,450 amendment to the Water Treatment Plant 2026 budget to cover the over-budget amount.
Get email alerts on the Infrastructure Contracts topic
No spam. Unsubscribe anytime.
The Mandan City Commission voted July 7 to award a contract to Car Coatings LLC for the South Side Reservoir coating project and to increase the Water Treatment Plant 2026 budget by $37,450 to cover the shortfall.
Jerrick told commissioners that bids were opened May 28 and "we received bids from 5 contractors and the apparent low bid was Car Coatings for a total of $163,450," an amount staff said exceeds the budgeted authorization for 2026. Commissioner Sjoberg moved to award the contract and the motion was seconded; roll call votes recorded unanimous support among those present. The contract award includes a recommended budget amendment so the work can proceed this construction season.
Staff described this work as routine maintenance — a protective seal coating to match the reservoir's existing finish — not a decorative treatment. Commissioners heard no objections during discussion and approved the motion. The city will publish contract details and a project schedule as procurement paperwork is finalized.