Board approves final adjustments on Sesame Street and Addison Creek projects

Village of Bensenville Village Board · June 25, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Trustees approved a final decrease of $152,157.99 on the Sesame Street reconstruction project (bringing final to $2,282,825.27) and approved a $211,736.17 increase on Addison Creek Stormwater Phase 2 (final $2,891,342.79) citing dewatering, excavation and soil conditions.

The board approved a final change order for the Sesame Street reconstruction SSA project decreasing the contract by $152,157.99, for a revised final contract amount of $2,282,825.27. Staff said unit-price balancing produced the savings and that the SSA (special service area) charges to property owners will be reduced accordingly.

On the Addison Creek Stormwater Phase 2 project, staff described soils and groundwater challenges that required additional dewatering, excavation and stone replacement. The board approved change order No. 2, adding $211,736.17 to bring the final contract to $2,891,342.79. Staff praised the contractor for completing the work under difficult conditions.