Board approves final adjustments on Sesame Street and Addison Creek projects
Summary
Trustees approved a final decrease of $152,157.99 on the Sesame Street reconstruction project (bringing final to $2,282,825.27) and approved a $211,736.17 increase on Addison Creek Stormwater Phase 2 (final $2,891,342.79) citing dewatering, excavation and soil conditions.
Get email alerts on the Capital Projects Changeorders topic
No spam. Unsubscribe anytime.
The board approved a final change order for the Sesame Street reconstruction SSA project decreasing the contract by $152,157.99, for a revised final contract amount of $2,282,825.27. Staff said unit-price balancing produced the savings and that the SSA (special service area) charges to property owners will be reduced accordingly.
On the Addison Creek Stormwater Phase 2 project, staff described soils and groundwater challenges that required additional dewatering, excavation and stone replacement. The board approved change order No. 2, adding $211,736.17 to bring the final contract to $2,891,342.79. Staff praised the contractor for completing the work under difficult conditions.