County roads official reports M16 paving progress, bridge replacement on Woodland Road
Summary
Chris Frederickson reported crews are shouldering the M16 paving project (over halfway complete with line painting to follow), installed guardrail on M16 north of 1100, and are replacing a bridge on Woodland Road with a culvert/low-water crossing; completion timing is weather dependent.
Get email alerts on the Transportation topic
No spam. Unsubscribe anytime.
Chris Frederickson delivered the secondary roads update, describing progress on M16 paving and shouldering, guardrail installation and a bridge replacement project on Woodland Road.
Frederickson said paving crews "are out there shouldering now" and that work on M16 is "over halfway down," with line painting expected once shouldering is complete and the road reopening to follow. He told the board crews installed a guardrail on the M16 bridge north of 1100 and that work on Woodland Road (between 2 and 300th) involves removing the old bridge structure and replacing it with a culvert or low-water crossing; he said final completion is weather dependent.
Frederickson also reported ditching and snow-trap removal in other county areas, hauling rock for spring operations and continued blading/spot rocking as needed. Board members thanked road staff for addressing potholes and trap-related issues.