Board approves change orders for South El Monte High modernization after months-long dispute
Summary
Trustees approved multiple change orders for the South El Monte High modernization project and a resolution to exceed the 10% change-order contingency limit. District staff said negotiating reduced Rancho Pacific Electric’s delay claim from roughly $364,000 to a $118,000 settlement.
Get email alerts on the Construction topic
No spam. Unsubscribe anytime.
The board approved change orders for the South El Monte High School modernization and adopted a resolution authorizing change orders that exceed the 10% contingency limit of Public Contract Code section 20118.4. Staff described the project as a $35 million, multi‑prime modernization that encountered sequencing delays, COVID-era restricted access that obscured some conditions, and multiple unforeseen items requiring additional work.
District staff explained they negotiated down a delay/overhead claim from Rancho Pacific Electric from about $364,000 to a $118,000 final amount. District project staff and counsel described months of review, documentation requests for payroll and equipment, and legal negotiation before the contractor accepted the reduced offer. Project managers said the multi-prime delivery lowered initial contract contingencies and that several legitimate unforeseen costs still remained. The board voted 5–0 to approve the change orders and the related resolution.