Village approves multi‑phase West Park ice rink project, sets $50,000 fundraising goal
Summary
The Village Board voted unanimously to approve a multi‑phase West Park ice rink project including spring concrete work under the pavilion; the West Park Improvement Team seeks $50,000 and has raised $5,750 toward Phase 2.
Get email alerts on the Parks Recreation topic
No spam. Unsubscribe anytime.
The Village of Sheffield Board on Dec. 9 approved a multi‑phase plan to install a 30x60 ice rink in West Park and authorized the village to assume responsibility for future maintenance once phases are complete. President Mary Lanham welcomed members of the West Park Improvement Team and the trustees voted 6‑0 to proceed after Trustee Pratt moved the motion and Trustee DeVoss seconded it.
The team described a phased schedule: Phase 2 — pouring concrete under the existing pavilion — to begin in the spring, with fundraising and donation requests to follow; Phase 3 will focus on electrical upgrades for power and lighting, and Phase 4 would add a chiller when funds permit. "The Goal is $50,000 and is currently at donations received in the amount of $5,750 towards Phase 2," the West Park Improvement Team reported. The group said it hopes Phase 2 can be completed before the June 2025 Carnival.