Public Works Director Tom DiPietro presented condition assessments showing an average sidewalk/path score of 75/100 and a road PCI around the low 70s, and warned that current funding levels will let conditions decline materially over a decade without increased investment. Council discussed whether to reallocate existing capital funds or prepare a ballot measure for additional maintenance funding.

Public Works Director Tom DiPietro presented condition inventories and multi‑year capital modeling that showed current funding will not sustain the city's sidewalks, shared‑use paths and roads at present service levels.

DiPietro said the sidewalk/shared‑use path inventory (surveyed with an external vendor) shows a citywide average condition score of 75 out of 100: "the average citywide condition for the sidewalk and stuff combined is 75 out of a 100." He described a dataset of 12,280 mapped deficiencies and said about 1,100 are severe while most are minor.

Using a deterioration model, staff showed that at roughly $500,000 per year for sidewalks and shared‑use paths the city's present average (around 77 in the modeling) would decline to roughly 56 over ten years. "At about a $500,000 per year, the sidewalk and shared gene path, we keep about the same quality... our score of 77 currently in about 10 years is predicted to go down to about 56," DiPietro said during the presentation.

On roads, staff presented a similar analytic framework and proposed a paving CIP of about $1.25 million for FY27. DiPietro said the city's pavement condition index was in the low 70s and that maintaining that average would require increasing periodic investment to a multi‑year stable funding level.

Councilors debated near‑term choices: whether to reallocate programmed funds (including Pennies for Paths and one‑time grant carryforwards) or prepare ballot language for more durable, voter‑approved funding. Staff said the Pennies for Paths reserve was about $885,000 at the end of FY25 but that much of the balance is already programmed for projects; they cautioned that spending the reserve on maintenance could reduce matching grant leverage.

Council requested a prioritized 'hot spot' list (the mapped severe deficiencies) and dollar estimates for fixing those locations before deciding on a financing approach or a ballot question.