Smithton reports smooth chip-and-seal completion; Wolfmeier to coordinate St. Johns parking-lot work
Summary
The village reported chip-and-seal street work finished without complaints; trustees said heat affected the oil quantity and that contractor Wolfmeier will coordinate a separate parking-lot job for St. Johns. The Knab Road/White Oak area is planned for next year.
Get email alerts on the Streets And Highways topic
No spam. Unsubscribe anytime.
The July 28 minutes state that the village's recent chip-and-seal work was completed and that there were no complaints about vehicles driving on the oil. The record notes that the summer heat affected the amount of oil required for the project.
Contractor Wolfmeier will work directly with St. Johns on that parking lot because the village had run out of oil during the project. Trustees also noted a plan to oil-and-chip the area near Knab Road and White Oak next year. No contract amounts, change orders, or resident complaints were recorded beyond the summary in the minutes.