Ameren advisor recommends VFDs for Smithton wastewater plant; utility may cover 80% of cost

Village of Smithton Committee as a Whole · July 28, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

An Ameren Illinois advisor told Smithton trustees that installing variable-frequency drives (VFDs) at the wastewater plant could cut energy use; Ameren would cover about 80% of the VFD cost and will connect the village with qualified contractors.

Rob Moss, a small-business energy advisor with Ameren Illinois, told the Village of Smithton on July 28 that installing variable-frequency drives (VFDs) on wastewater-plant motors could reduce run time and energy use. He said Ameren would cover 80% of the cost and that the utility charges no fee for an on-site meeting.

Moss recommended starting by meeting with electricians and insulation contractors and coordinating incentive applications with Ameren. He advised that projects with incentives over $15,000 require preapproval and that contractors must be registered with the Illinois Commerce Commission; he offered to put Village Administrator George Liyeos in touch with contractors. The minutes also note that insulation and lighting opportunities were discussed and that the village should check whether the new lift-station motors already have VFDs so an incentive application can be completed if appropriate.

The presentation referenced prior lighting and thermostat upgrades and noted recent HVAC and roof replacements, suggesting insulation could be a next step for additional savings. Moss also suggested reviewing lighting at the Senior Center and the village shed for potential upgrades. The minutes do not list estimated total project costs, timelines, or a decided contractor; trustees directed staff to follow up with the contacts Moss promised to provide.