Trustees hear water-plant update; lead-line potholing set to begin Sept. 30
Summary
President Samples reported the water plant has been running but brine skid pumps on the softener system are failing to hold prime; the vendor is investigating. Potholing for lead service lines is scheduled to start Sept. 30, 2024.
Get email alerts on the Water Infrastructure topic
No spam. Unsubscribe anytime.
President Richard Samples updated trustees that the water plant has been running all week but the softener-plant brine skid pumps are not holding prime on their own; the vendor working on the plant is investigating the problem. Samples also told trustees that oil-and-chip street work is complete and the village splash pad is closed for the season.
Samples said potholing for lead service lines will begin Sept. 30, 2024. He also advised the board that the village received a reimbursable grant for generators at lift stations, noting the village must purchase generators first and seek reimbursement under the grant terms.