The county approved a building permit allowing new antennas, an 8x8 equipment shelter, a 35 kW diesel generator and a 500-gallon propane tank to be installed on an existing communications tower without altering the tower structure.
Get email alerts on the Communications Infrastructure topic
No spam. Unsubscribe anytime.
The board reviewed a building permit from a utilities company to remove an existing 11x25 structure at a tower site and install new antennas and communications equipment while leaving the tower structure unchanged. The application included an 8x8 equipment shelter, a 35-kilowatt diesel generator and a 500-gallon propane tank.
After questions about the installation, a motion to approve the permit was moved and seconded; the board carried the motion by voice vote. Staff will follow standard permitting procedures regarding placement and safety of the generator and fuel storage.