Council approves $133,215 WRH change order; consent package includes $932,777.27 in pay requests

Anamosa City Council · June 11, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved a $133,215.07 change order for the wastewater treatment plant flow EQ basin project, reconciling a previously cited $201,787.77 figure. The council also approved a consent pay-request bundle totaling $932,777.27 that includes payments to WRH Inc., HR Green and Snyder & Associates.

City staff explained that WRH Inc. submitted a $133,215.07 change order to reconcile an earlier line item; staff said the previously mentioned $201,787.77 change order had not involved any exchanged funds and the corrected amount reduces the total project cost to approximately $4,190,000. "The change order that we recently approved on the 24th was for $201,787.77... Instead, it was this change order for $133,215.00," a staff member said.

Council approved the WRH change order and then approved a consent pay request package totaling $932,777.27 covering nine items, including WRH Inc. and engineering invoices. Staff noted the WRH contractor's application for payment includes the corrected $133,215 change order, not the larger earlier figure.