Board discusses wastewater polymer system, IEPA permit and procurement options; estimate roughly $300,000

Village of Spring Grove Village Board · January 20, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Village staff and consultants reviewed a polymer system for the wastewater treatment plant that received an IEPA permit and discussed pursuing design-bid versus design-build procurement; the project estimate in the minutes is roughly $300,000.

Village staff reported meeting with Scott Trotter of Trotter Engineering about a polymer system for the wastewater treatment plant that the minutes say has been approved with an IEPA permit. The discussion focused on whether to solicit bids under a traditional design-bid approach or to pursue a design-build contract with Trotter Engineering performing design and construction oversight.

Minutes record an estimated project cost “to cost roughly $300,000” though the transcript numbers are partially garbled; trustees and staff discussed that a design-build delivery might permit adjustments during work to reduce costs. No procurement decision was made at the Jan. 20 meeting; the board discussed next steps including whether to go out to bid or to request a design-build proposal.

The board did not adopt a procurement schedule or authorize funds at the meeting; staff indicated further analysis and possible future agenda action would follow.