US‑278 bridge and corridor project moves toward federal clearance; county flags $190M shortfall

Public Facilities and Safety Committee · August 19, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

County staff said the US‑278 environmental document has been submitted to Federal Highway and design is at roughly 30% with a 60% milestone expected in Sept. 2025; construction finish dates are several years out and staff identified an approximate $190 million funding gap.

County transportation staff told the committee that municipal consent allowed DOT to submit a Finding of No Significant Impact (FONSI) to Federal Highway and that staff expect a federal response by the end of September. "That document has been submitted to Federal Highway, and, we're expecting a notice back and approval hopefully by the end of September," staff said.

Presenters described the design timeline: the project is at about 30% now; staff expect to reach 60% in roughly one year, then begin right‑of‑way and utility coordination. From that point, another 2.5–3 years of construction are estimated for the bridge portion. Staff also identified a funding shortfall: "If November doesn't pass, we have 2.5 years to figure out how we're gonna solve a $190,000,000 delta," a presenter said, and said the county has contingency plans but will need additional funding decisions if the referendum fails.