Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Property Remediation topic

No spam. Unsubscribe anytime.

Land bank says 518 First Street (Rengo Oil) project extended after excavation issues; completion now mid-May

Manistee County Land Bank Authority · April 20, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Project Manager Katie Gruenberg told the board that unexpected site conditions at the Rengo Oil parcel (518 First Street) required a change order approved with the State Land Bank Authority, extending completion to mid-May while environmental review continues.

Project Manager Katie Gruenberg reported that excavation at 518 First Street (the Rengo Oil site) uncovered site conditions that required a change order and additional time. She said the change order was reviewed with the State Land Bank Authority and approved, and that the project is now anticipated to be completed in mid-May.

Board members discussed the original project scope and the environmental review process; Ms. Gruenberg noted environmental findings may affect timing and costs for this and other properties. No formal vote was taken at the meeting on this item.