Logan Energy Storage Project: county hears schedule, deliveries and contamination issue
Summary
Alan Sargent updated the commission on the Logan Energy Storage Project: 102 batteries on site with 37 set on foundations, 136 targeted battery capacity, inverter and substation work in progress, and a mid-December completion target; one contaminated battery was removed after water intrusion.
Get email alerts on the Energy Project topic
No spam. Unsubscribe anytime.
Alan Sargent, project representative, told the board the site has 102 batteries on-site, with 37 already set on foundations and a target of 136 total. "102 batteries on-site. Got 37 that have been set on foundations already. 136 is the total we're shooting for," he said, and noted deliveries pause after the next shipments with the next bulk delivery window scheduled for mid-August.
Sargent reported some logistics challenges, including one battery that suffered water contamination after a door was not latched and will be removed and replaced. He said the contractor expects to complete deliveries and on-site equipment installation by Aug. 26 for final deliveries and remains optimistic about a mid-December overall completion date, depending on weather.