Board reviews FY26 School Maintenance Grant funding for Phase II of Beckemeyer roofing project

Hillsboro Community Unit School District #3 Board of Education · October 14, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Superintendent McBrain said FY2025 funds were used for Phase I of the Beckemeyer roof and FY2026 grant funds are planned to cover a portion of Phase II, focused on main hallways and 2nd/3rd grade classrooms.

Superintendent McBrain presented the district’s plan for use of the FY2026 School Maintenance Grant: funds will be allocated toward Phase II of the Beckemeyer roof project, specifically roofing the main hallways and the 2nd and 3rd grade classrooms. He noted FY2025 funds covered Phase I of the Beckemeyer roof.

No formal vote was recorded on the funding allocation at the Oct. 14 meeting; the item was discussed to inform the board about planned capital maintenance priorities and grant alignment.