Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the School Maintenance topic
No spam. Unsubscribe anytime.
Board reviews FY26 School Maintenance Grant funding for Phase II of Beckemeyer roofing project
Summary
Superintendent McBrain said FY2025 funds were used for Phase I of the Beckemeyer roof and FY2026 grant funds are planned to cover a portion of Phase II, focused on main hallways and 2nd/3rd grade classrooms.
Get email alerts on the School Maintenance topic
No spam. Unsubscribe anytime.
Superintendent McBrain presented the district’s plan for use of the FY2026 School Maintenance Grant: funds will be allocated toward Phase II of the Beckemeyer roof project, specifically roofing the main hallways and the 2nd and 3rd grade classrooms. He noted FY2025 funds covered Phase I of the Beckemeyer roof.
No formal vote was recorded on the funding allocation at the Oct. 14 meeting; the item was discussed to inform the board about planned capital maintenance priorities and grant alignment.
