Council accepts Mid Atlantic Asphalt low bid for basketball court resurfacing, pending clarifications
Summary
The Council approved the updated low bid from Mid Atlantic Asphalt for basketball court resurfacing ($25,320) pending satisfactory responses to follow-up questions; the vote was 6-0.
Get email alerts on the Capital Improvement topic
No spam. Unsubscribe anytime.
Peter Nagrod reviewed responses to the 2026 Basketball Court Resurfacing RFP and reported that all bids exceeded FY26 funds. The low bidder from 2025, Mid Atlantic Asphalt, submitted an updated 2026 cost of $25,320 for the same work. Peter Nagrod moved to approve their updated bid; John Porter seconded. After brief discussion the Council voted 6-0 to accept the Mid Atlantic bid pending satisfactory answers to outstanding questions.
The acceptance is contingent on those clarifications and does not constitute final contract execution; staff will follow up with the bidder and report back to the Council.