Board approves MFT contracts for pavement patching and additional sidewalk work

Village Board of Bensenville · August 27, 2025

Summary

Trustees authorized a pavement-patching contract increased to $200,000 to take advantage of low bids and approved a sidewalk removal/replacement contract up to $100,000 after staff recommended using the full allocations.

Public Works presented two MFT-funded projects and the board approved both resolutions. Joe said Chicagoland Paving submitted the lowest bid of $165,000 for the pavement-patching program and staff recommended increasing the contract to the $200,000 allocation to get additional patching done; the board approved the contract not to exceed $200,000.

On the sidewalk program, the low bid was just over $72,000 but staff recommended increasing to the full $100,000 allocation to replace more sidewalks; trustees approved the increase and authorized the contract amount up to $100,000.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source