Village hires EEI to design Belmont/Addison/Center CDBG roadway and water-main improvements

Village Board of Bensenville · August 27, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board authorized a $145,501 design contract with Engineering Enterprises Inc. for a CDBG-backed roadway and water-main project after staff said the village received $600,000 in DuPage County CDBG funds toward an estimated $2.7 million project.

The Village Board approved a design agreement with Engineering Enterprises Inc. (EEI) for the Belmont, Addison and Center roadway and water-main improvement project. Public Works staff said the village was awarded $600,000 in DuPage County Community Development Block Grant funds to help cover an estimated total construction cost of about $2.7 million; after negotiations, EEI proposed a design fee of $145,501 (about 5.3% of estimated construction cost).

Joe said the scope will include roughly 3,500 linear feet of 8- and 12-inch water main, about 1,000 feet of new storm sewer, pavement reconstruction, curb-and-gutter replacement, ADA sidewalk upgrades and landscaping. Staff recommended approval to begin design so the project can proceed in 2026.