Officials report progress on wastewater upgrade, expensive filter replacements and low reservoirs

City of Amsterdam Common Council · October 22, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City staff updated council on a $30.113 million wastewater treatment plant upgrade schedule and expensive filter replacements at the drinking-water plant; one set of filters lasted seven years rather than the expected 20–30, costing roughly $2.15M across two rounds, and reservoirs remain at low levels, prompting conservation reminders.

City staff provided multi-project infrastructure updates including the wastewater treatment plant upgrade, drinking-water filter replacements and reservoir conditions.

Zach, a city project staffer, said the wastewater treatment plant upgrade is a roughly $30.113 million project and staff completed a 90% review; they expect state agency (EFC and DEC) comments by the end of November and then will put the project out to bid. On drinking-water operations, staff said the first round of replacement filters (three) cost about $850,000 and an additional set for the final phase was about $1.3 million; previously installed filters were expected to last 20–30 years but some lasted only seven, prompting replacement. New filters have increased run time by about 10–20% and reduced water and chemical use.

Staff also reported reservoir levels remain low (visually around 25–30% in some locations) and urged continued voluntary conservation. Council thanked staff for the progress; no votes were required for the updates.