Hartland awards M‑59 water main construction contract to low bidder for $1.217 million
Summary
After vetting four bids and adding a 10% contingency, the board approved awarding the M‑59 water main installation contract to Bidagari Contractors at an amount not to exceed $1,217,411.80; the work will be funded through the township's water bond proceeds.
Get email alerts on the Water Infrastructure topic
No spam. Unsubscribe anytime.
Staff presented the construction bids for the M‑59 water main installation, reported the low bid and recommended awarding the work to the low bidder. The board approved a motion to award the contract to Bidagari Contractors for an amount not to exceed $1,217,411.80 and authorized the public works director to act on the township's behalf regarding the project.
Staff noted the inclusion of a 10% contingency to account for typical underground‑work unknowns and said all project funding will come from the township's water bond proceeds. Trustees approved the motion by voice vote.