Malibu solar and microgrid projects move forward with contract amendment and early procurement

Santa Monica-Malibu Unified School District Board of Education · July 17, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board approved a contract amendment and early procurements for Malibu site microgrid and solar work, including long‑lead purchases of panels, switchboards and battery systems. Staff said quick‑connect generators already support emergency power and that Schneider Electric will assist with microgrid controls and federal investment tax credit applications.

District sustainability staff and consultants updated the board on progress at the Malibu sites, where quick‑connect generators are already installed and early procurement of long‑lead items (solar panels, energy control center components and battery storage) is underway to keep the projects on schedule. Austin Toyama said the early purchases enable the district to secure federal investment tax credits and help meet installation timelines: panels were ordered for the hillside system in December 2025 and key energy control center components were ordered in March 2026 to support fall 2027 and winter 2027–28 installation windows.

The contract amendment before the board separates design work into phased DSA submissions (hillside solar, battery, microgrid) and clarifies Schneider Electric's role in designing the energy control center and assisting with interconnection submittals to SoCal Edison. The board approved the amendment and staff said they will return with updates as the projects advance.