Commissioners probe payback, grants after trail work: $360,000 spent, about $290,000 reimbursed so far
Summary
Staff told the board that roughly $360,000 has been spent on the Enka/Anka Heritage Trail design and about $290,000 has been reimbursed (80% rate). Commissioners asked whether NCDOT or MPO would reassign the remaining funds and whether TDA grants applied to county-owned park facilities could support connectivity work.
Get email alerts on the Public Funding topic
No spam. Unsubscribe anytime.
During questioning, staff clarified the project's funding timeline and reimbursements. The presenter said the NCDOT had allocated approximately $4,800,000 for the trail and that TDA awarded roughly $6,000,000 for the Anchor Recreation Destination. "We have been reimbursed around $290,000, which means that we have only spent around $360,000," staff said, adding that reimbursements were at about an 80% rate.
Commissioners asked whether inactive NCDOT funds would revert to NCDOT, be routed to the MPO, or be available for proposed county-controlled connectivity work. Staff said those discussions would be with NCDOT and the MPO and that release or reallocation decisions would be made through those channels; commissioners pressed for clarity about which projects the MPO might choose to fund.