Highway staff: 2026 chip-seal largely finished; fog seal, striping and culvert work remain
Summary
County highway reported mowing started May 26, the 2026 chip-seal contract is complete though county crews must apply fog seal and striping, and crews are working on culverts near Astoria and Brookings County Road 8 with temporary daytime closures planned.
Get email alerts on the Roads topic
No spam. Unsubscribe anytime.
Brian, representing the highway department, told commissioners that mowing began May 26 and that the county's 2026 chip-seal contract is "wrapped up" but county forces still need to apply fog seal and complete striping later this month and into July.
He also reported culvert repairs and installation near Astoria and Brookings County Road 8, noted temporary daytime road closures for those repairs and said the county will follow with an asphalt project later in the summer.