Elevated storage tank nears substantial completion; Sullivan Street improvements funded

Village of Industry Board of Trustees · December 4, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Benton Engineering reported the elevated storage tank is nearing substantial completion and undergoing a second disinfection; funding was awarded for Sullivan Street improvements and IDOT held a recent kick-off meeting.

Doug of Benton Engineering updated the board that the elevated water storage tank is approaching its substantial completion deadline and is "currently being disinfected for the second time." He added that funding was awarded for Sullivan Street improvements and that there was a kick-off meeting with IDOT two weeks earlier. Attorney Laegeler asked whether the Fire Department could add an antenna to the water tower; Doug said that would likely need to wait until after substantial completion.

The report indicates the water tank work is in final commissioning and that the Sullivan Street project has funding and an IDOT coordination step underway. The minutes do not list a final completion date for the tank or funding amounts for the Sullivan Street work; the board did not take separate motions on these updates during the portion of the meeting recorded in the minutes.