F & K preconstruction meeting set; Chamberlain Biz Park work funded by Ready 2
Summary
Staff reported a preconstruction meeting with F & K Construction for the Chamberlain Biz Park water extension (funded through Ready 2), with notice-to-proceed on Aug. 24 and a 180-day construction window; staff emphasized a Sept. 30 drawdown milestone.
Get email alerts on the Development topic
No spam. Unsubscribe anytime.
Staff updated the board on the Chamberlain Business Park water extension and its Ready 2 funding.
Presenter (speaker 3) said the preconstruction meeting with F & K Construction occurred today and the water portion will follow the same meeting schedule as previous projects. Staff said the notice-to-proceed is Aug. 24, starting a 180-day construction period, and that the project must hit drawdown milestones by Sept. 30 to secure grant/loan disbursements. "I wouldn't expect really any water materials being ordered that time...sewer their their plan is to put in all sewer 1st and then do all the water," the presenter said.
Staff outlined sequencing (sewer first, then water), funding breakdown notes (Ready 2 will cover water/wastewater with approximately $1.4 million for water/waste and roughly $1,000,000 for the road), and how the project will deliver internal hookups for future development. Board members asked clarifying questions about alignment, pipe size and loop connections; staff said a 10-inch main will be installed where appropriate.