Chair moves to pay Rex Construction $104,229 for Lehi line work
Summary
The Rochester water board approved Pay Application No. 8 to Rex Construction, authorizing payment of $104,229.25 for completed work on Jefferson and Pontiac and directing staff to follow up on limited punch-list items the contractor will rework.
Get email alerts on the Contracts topic
No spam. Unsubscribe anytime.
The board approved payment to Rex Construction for work on portions of the Lehi line, including segments on Jefferson and Pontiac.
Presenter (speaker 3) recommended payment of Pay Application No. 8 to Rex Construction in the amount of $104,229.25 and explained staff will issue a change order asking the contractor to rework a small number of locations closer to the road where the walk-through identified issues. "for the payment of the contractor in the amount of a $104,229.25," the presenter said. The Chair made the motion and the board approved the payout by voice vote.
Staff confirmed funds remain available to complete any required replacements and that the change order will direct Rex to return and verify the questioned locations. Board members emphasized verification and documentation before final acceptance of the work. The board did not add new funds; staff said existing project contingency and remaining line-item balances will cover the punch-list work.
The motion approved the pay application and instructed staff to keep the board informed about any subsequent change orders and the contractor's corrective work schedule.