Eversource cutover tentatively set for the 11th; easement package filed

School Board HVAC Project Committee · August 4, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Project staff said easement documents were signed and sent to the town clerk and the utility has tentatively scheduled the electrical cutover for the 11th, with a rain date of the 12th.

During the status update, Ben reported progress on utility coordination: the easement package for the power work was completed, signed and sent to the town clerk and the project attorney will file it. He told the committee the utility (Eversource) has tentatively scheduled a cutover for the 11th with a rain date on the 12th.

Ben also noted the automatic transfer switch (ATS) is installed and wired in the electrical room and that only the cutover remains. He characterized this as a critical near-term milestone for powering equipment needed for the school-year startup.