Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Hvac topic
No spam. Unsubscribe anytime.
HVAC upgrades on track at Polson and Hand; crews prioritize 43 penthouse units ahead of school opening
Summary
Project staff reported major HVAC equipment is installed and commissioning has begun; crews are prioritizing replacement of 43 penthouse units so the buildings can open on schedule, with manufacturer startup and weekend work planned.
Get email alerts on the Hvac topic
No spam. Unsubscribe anytime.
Chair opened the School Board HVAC Project Committee meeting, and Ben provided a detailed progress report on the Poulsen/Polson and Hand HVAC projects. "We are on track to start school in 3 weeks," Ben said, and noted staff will start on Monday, Aug. 24. He said crews are prioritizing direct replacements of 43 penthouse units that provide heating and cooling to spaces used last year.
Ben described a tight schedule for commissioning: condensers and air handlers are set, a controls crew and electrical crew are following mechanical installs, and the manufacturer's representative will start firing systems next week with crews working two Sundays to meet the timetable. He warned that supplementary cooling systems (VRF) are scheduled to be phased in later: "don't advertise a full online till, like, at least October," he said. Committee members pressed about bottlenecks; Ben and staff said long-lead materials are tracked and the items needed for building startup are in hand.

