Consultant outlines entitlements and timelines: 1–2 years to market, additional months for permits
Summary
3 d Strategies told the board that, after marketing (estimated 1–2 years), tenants would need to navigate conditional-use or special-use permits and conforming rezones and allow roughly six to 12 months for tenant-improvement permitting and construction.
Get email alerts on the Timing And Entitlements topic
No spam. Unsubscribe anytime.
The consultant laid out likely timelines and entitlement steps for any successful leasing or conversion. Dan Merar said a realistic marketing window to identify suitable tenants for a district campus is about one to two years; after a tenant is identified, entitlement steps (conditional-use permit or special-use permit and a conforming rezoning where required) would likely run concurrently with tenant-improvement permitting and construction, which Merar estimated could take "6 to month 12 months" depending on concurrency.
Merar emphasized that conforming rezoning for PQP-designated sites typically goes to the city council but is processed as a conformity step rather than a general-plan amendment; he noted general-plan amendments are more time-consuming and processed on a set schedule. Board members asked clarifying questions about whether zoning designations would discourage tenants and how lease terms (often 15-year terms) interplay with tenant investment in improvements.