Nags Head pickleball project sees $192,000 cost increase after unsuitable soils discovered
Summary
County manager reported excavation at the Nags Head pickleball facility uncovered unsuitable soils requiring additional excavation and fill, increasing project cost by roughly $192,000; officials said savings elsewhere keep the project within the overall budget and estimated an end‑of‑October completion.
Get email alerts on the Parks Infrastructure topic
No spam. Unsubscribe anytime.
County staff updated the board on construction at the Nags Head pickleball project and reported an approximately $192,000 cost increase after excavation revealed unsuitable soils requiring deeper excavation and additional imported fill. "As they were excavating, there were some unsuitable soils ... That resulted in about a $192,000 increase in the cost," the county manager said.
The county manager noted that prior cost savings of $300,000–$400,000 on the project offset the additional expense and that tourism board funds are sharing half of the increased cost. Staff estimated the site will still be completed by the end of October and advised commissioners they wanted to flag the change to avoid surprises later in construction closeout and accounting.