Consultants present wastewater master plan, estimate $24.5M in multi‑year projects
Aug 5, 2026
Aug 5, 2026
Hazen and Sawyer presented a wastewater master plan for Oldsmar that finds the plant performing above model expectations, outlines resiliency work after past floods, and proposes a $24.5 million multi‑year capital program with $2.6M in year‑one needs and grant-funded items.
The full story
Tim Ware of Hazen and Sawyer told the Oldsmar City Council the wastewater master plan is a long‑term roadmap covering the treatment plant, collection system, pump stations and pipelines. He said the plant is rated for roughly 2,250,000 gallons per day and staff currently operate it more efficiently than the model predicts.