Board hears Year 6 solar project fell short of savings; staff to meet with vendor

MSD of New Durham Township School Board · February 13, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board was told the district's solar project 'did not meet savings goal' for Year 6. District staff plans follow-up meetings with Performance Services and a Fronius-certified installer to review performance reports and contract issues.

The MSD of New Durham Township school board heard that the district's Year 6 solar project "did not meet savings goal," and staff said they will dig deeper into the performance reports and related contracts.

Superintendent Brian Ton and district staff reported that Year 6 performance fell short of projected savings. District staff, including Christopher deBruyn, said they will meet next week with Performance Services and with a Fronius-certified company to review the system's communications and the original installation. According to the minutes, Fronius advised that keeping a spare inverter on hand "would not be a good idea" because it would not be covered under warranty and recommended working with a Fronius-certified company for replacements.

The discussion noted concerns about whether some components were installed correctly at the outset; the board did not take action beyond directing staff to pursue vendor meetings and a bid to find a Fronius-certified contractor. The minutes do not provide projected cost estimates or a timeline for repairs; those details were not specified.