Staff: Water treatment plant in commissioning; state operational testing targeted for early April
Summary
Staff reported the water treatment plant is in commissioning and functional testing, working through an issues log they estimated at about 100–200 items, and said they plan to notify the state and target early April for operational water-quality testing.
Get email alerts on the Water Treatment topic
No spam. Unsubscribe anytime.
A staff presenter said the new water treatment plant has entered a commissioning and functional testing phase and that teams are simulating alarm conditions to verify responses and troubleshoot instrumentation and programming.
The presenter described an iterative process: "When you change one parameter, it affects about five things down the line," and said the team has been working off "an issues log that's about 100 to 200 deep for the past 3 months." Staff said, once internal testing gives strong confidence, they will notify the state and pursue operational water-quality testing; the presenter added the team is "targeting early April."
No formal action or vote was taken; the item was presented as a department report and staff said the next procedural step is to complete internal testing and then begin state-run operational testing.