Waco High construction schedule shifts as contractors claim weather-day extension; district says Fall 2025 occupancy unaffected
Summary
Board reviewed a time extension under the contract's weather-day provision that moves completion dates for phases of Waco High School construction (Phases 1 & 2 to May 22, 2025; Phase 3 to Jan. 19, 2026). District officials said planned Fall 2025 occupancy is not delayed.
Get email alerts on the Construction Schedule topic
No spam. Unsubscribe anytime.
During the Aug. 22 meeting trustees reviewed a contract time extension tied to the project's weather-day provision. As reported to the board, Phases 1 and 2 completion dates shifted from April 18, 2025, to May 22, 2025, and Phase 3 moved from Dec. 15, 2025, to Jan. 19, 2026. Minutes state the contract's weather-day clause allows time extensions without increasing the contract sum when weather days are exceeded.
Board minutes note the district's planned occupancy for Fall 2025 remains unaffected by the schedule adjustment. The item was presented as an approval of Change Order #1 for a time extension under the existing contract provisions; final documentation and any cost implications were not detailed in the minutes.