Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Secondary Roads topic
No spam. Unsubscribe anytime.
Turner pay application for Secondary Roads admin addition includes partial retainage release to subcontractors
Summary
Turner Construction’s Application for Payment No. 20 for the Secondary Roads administration addition was filed; the submission includes a partial release of retainage totaling $27,268.16 for named subcontractors and requests $37,198.50.
Get email alerts on the Secondary Roads topic
No spam. Unsubscribe anytime.
Turner Construction submitted Application for Payment No. 20 for the Secondary Roads Administration addition and included a partial release of retainage detail listing subcontractor partial payouts. The pay packet identifies an amount requested in the current application ($37,198.50) and lists subcontractors with partial retainage release amounts totaling $27,268.16 for items such as millwork, metal framing/drywall and other trades.
Turner’s project update and pay application continuity sheets show direct-work totals and the continuation sheet detail linking subcontractor invoices and retainage, and an accompanying Farnsworth Group certification endorses the payment request. County staff typically review subcontractor close‑out materials and required release documents before authorizing partial retainage release to vendors.
